Friday, April 13, 2012

LaPine Oregon Project / Doug Steidl's Shop / April 2012

Another successful week on Doug Steidl's shop. Here are some photos of the procedure for excavation and compaction for the concrete portion of the shop.


We always tie posts in with #4 re-bar.

We use a stitch nail procedure on all of our buildings that have a concrete slab.

Slab Pour

Starting of of finish grading.

Finish grading

Notice you barely see the imprints from the ready mix truck. That's what we call good compaction.

Roman slate stamped entry. Hopefully a nice surprise for Doug :).

New shop floor.

First stages of final prep.

Southeast corner of final building elevations.

West side building elevations.

Concrete anchor tie down system. 

Back-fill material for concrete prep work.

The dreaded stump pile.

We tie in all post foundations with #4 re-bar.

Compaction fro final prep for concrete pour.

Entry pour.